The project will span 800 acres when completed, which could be in 2028 or later, depending on individual projects within the development. Currently, a project to build 3 bridges, 1 each on North Main, Jacksboro Hwy., and White Settlement Rd., is still coming along, despite a year-long delay. That was because TxDOT wanted to be certain of the structural design of each bridge. The bridges have to be complete before any river channeling or other infrastructure (including riverwalks along each waterway) can begin. The bridges should be complete in early 2020.